Balance Work Plan & Manhour Model
A repeatable recovery methodology: turn remaining ("balance") scope into a defensible, resource-loaded plan using manhour norms, productivity assumptions and a manpower histogram.
01Background
When a project slips, "just add manpower" is rarely a plan. The balance-work model exists to answer a harder question precisely: given the scope that remains, how many people — by discipline — are actually needed each week to finish on a target date, and is that number physically achievable on the available work fronts?
02Problem / challenge
Remaining quantities are often scattered across activities at different completion levels. Without converting them into manhours and then into a week-by-week manpower demand, recovery targets are just optimistic dates. The challenge is to build a model that is transparent, easy to update each cycle, and credible enough to commit to.
03My approach
- Extract remaining quantities (balance BOQ) per activity
- Apply manhour norms to get total remaining manhours by discipline
- Set productivity & working-calendar assumptions (hours/day, efficiency)
- Spread manhours across the recovery window → weekly manpower demand
- Test the histogram against site capacity; level peaks that aren't feasible
04Tools used
05Deliverables
- Manhour calculation sheet (balance BOQ → manhours)
- Manpower histogram by discipline & week
- Productivity assumptions register
- Resource-loaded recovery schedule
06Sample — manpower histogram
Manpower demand by week
Stacked by discipline, against the recovery window
07Result / impact
Converting balance scope into a manpower histogram turns recovery from a negotiation into a calculation. Management can see exactly what crewing is required — and whether the site can physically absorb it — before committing to a date.